Republic of the Philippines
Province of Compostela Valley
Cabidianan, Nabunturan, Compostela Valley
BIDS AND AWARDS COMMITTEE
CIVIL WORKS BID- OUT
4th Quarter, CY-2017
No. |
Name of Project |
Approved Budget for Contract |
Location |
Winning Bidder |
Name and Address |
Bid Amount |
Bidding Date |
Contract Duration |
|
1. |
CW17-001 17-5206 |
1 LOT CONTRACT: FURNISHING LABOR, EQUIPMENT AND MATERIALS FOR THE UPGRADING/IMPROVEMENT OF ELIZALDE-PANAMIN- ANITAPAN PROVINCIAL ROAD, MACO AND MABINI (ELIZALDE MALAMODAO-GOLDEN VALLEY SECTION)
(CONCRETING OF 8.4688KMS. ROAD, INSTALLATION OF 282PCS.-910MM. DIA RCPC, 84PCS.-1220MM. DIA RCPC, 24PCS.-1830MM DIA., RCPC WITH HEADWALL AND CONSTRUCTION OF 5.54466KMS. CONCRETE DRAINAGE LINED CANAL)
|
176,255,188.00 |
ELIZALDE-PANAMIN-ANITAPAN PROVINCIAL ROAD, MACO AND MABINI |
TAGUM BUILDERS CONTRACTORS CORPORATION & THREE W BUILDERS, INC.
(JOINT VINTURE) |
JESSIE G. ISALES – MANKILAM TAGUM CITY
VICTORIANO L. ADA – LAS PIÑAS CITY |
175,861,180.76 |
08-22-17 |
305 CALENDAR DAYS |
2. |
CW17-002 17-5208 |
1 LOT CONTRACT: FURNISHING LABOR, EQUIPMENT AND MATERIALS FOR THE UPGRADING/IMPROVEMENT OF NABUNTURAN-NUEVO ILOCO PROVINCIAL ROAD, PHASE II, NABUNTURAN AND MAWAB (LIBASAN-SAOSAO-BAWANI SECTION)
(CONCRETING OF 6.8499KMS. ROAD, INSTALLATION OF 255PCS. 910MM.DIA RCPC AND 10PCS.-1830MM.DIA. RCPC WITH HEADWALL AND CONSTRUCTION OF 1.267KMS. CONCRETE DRAINAGE LINED CANAL) |
75,900,000.00 |
NABUNTURAN-NUEVO ILOCO-PROVINCIAL ROAD, PHASE II, NABUNTURAN AND MAWAB, COMPOSTELA VALLEY PROVINCE |
ALONZO CONSTRUCTION |
NAPOLEON M. ALONZO – MATINA PANGI, DAVAO CITY |
75,713,481.71 |
08.22.17 |
140 CALENDAR DAYS |
3. |
CW17-003 17-5207 |
1 LOT CONTRACT: FURNISHING LABOR, EQUIPMENT AND MATERIALS FOR THE UPGRADING/IMPROVEMENT OF MAYAON-SAN ANTONIO PROVINCIAL ROAD, PHASE II MONTEVISTA AND LAAK (MAYAON-SAN ANTONIO SECTION)
(CONCRETING OF 12.080KMS. ROAD, INSTALLATION OF 390PCS. 910MM DIA, RCPC, 10PCS. 1220MM DIA RCPC WITH HEADWALL AND CONSTRUCTION OF 9.31759KMS. CONCRETE DRAINAGE LINED CANAL) |
200,000,000.00 |
MAYAON-SAN ANTONIO PROVINCIAL ROAD, PHASE II MONTEVISTA AND LAAK |
FFJJ CONSTRUCTION |
OSMEÑA L. PALANGGALAN – COTABATO CITY |
199,151,000.00 |
08.22.17 |
480 CALENDAR DAYS |
4. |
CW17-004 17-6619 |
1 LOT CONTRACT: FURNISHING LABOR, EQUIPMENT AND MATERIALS FOR THE RETROFITTING OF BASAK RCDP BRIDGE, NABUNTURAN (RETROFITTING OF 2 LINES, 9.88IN.M BRIDGE) |
2,916,253.05 |
BASAK,NABUNTURAN,COMVAL PROVINCE |
AMPLEX CONSTRUCTION & SUPPLIES |
JOHN PAUL S. TAMAYO – TUPI SOUTH COTABATO |
2,913,304.00 |
11.7.17 |
40 CALENDAR DAYS |
5. |
CW17-005 17-6251 |
1 LOT CONTRACT: FURNISHING LABOR, EQUIPMENT AND MATERIALS FOR THE DEEP WELL LEVEL II WATER SYSTEM AT PUROK SANTOL, BRGY. PANGI, MACO (INSTALLATION OF 1 UNIT 1.5HP CENTRIFUGAL PUMP AND MOTOR WITH 220 GALS PRESSURE TANK, WATER PIPELINES AND ELECTRICAL LINES) |
1,500,000.00 |
BRGY. PANGI, MACO |
ANCOR WATER RESOURCES |
ANDRES GENTUGAYA, JR. – MANKILAM TAGUM CITY |
1,498,584.44 |
12.5.17 |
80 CALENDAR DAYS |
We hereby certify that we have reviewed the contents and hereby attest to
the veracity and correctness of the data or information contained in this
documents.
Sgd. VIRGILIA S. ALLONES Sgd. DR. ROLANDO S. SIMENE Sgd. ARMANDO G. ATAKE Sgd.ENGR. RODERICK M. DIGAMON Sgd.DR. NEIL P. ESTOYA
BAC-Chairperson Vice-Chairman Member Member Member